Water Line Removal

2/26/14

Location: Bellevue, WA OCI was responsible for the removal of an asbestos concrete waterline suspended 5 feet above Kelsey Creek. The design required coordination with the fish window, evaluation of impacts to the stream, and addressing limited access to the site. OCI performed site visits, completed the design for the removal and streambank restoration, and
( Read more... )

Kelsey Creek at NE 8th Street Fish Passage Culvert Improvements

2/25/14

Location: Bellevue, WA Owner: City of Bellevue OCI was selected by the City of Bellevue as the prime consultant to complete full plans, specifications and engineer’s estimate of the proposed fish passage improvements within Kelsey Creek at the NE 8th Street culvert. The OCI team was responsible for the data collection and site reconnaissance, the